Industrial Engineering Miscellaneous


Industrial Engineering Miscellaneous

Industrial Engineering

  1. The distribution of lead time demand for an item is as follows :

    The reorder level is 1.25 times the expected value of the lead time demand. The service level is









  1. View Hint View Answer Discuss in Forum

    The expected value of lead time demand
    ⇒ 80 × 0.20 + 100 × 0.25 + 120 × 0.30 + 140 × 0.25 = 112
    Reorder level is 1.25 times the lead time demand.
    So, Reorder value = 1.25 × 112 = 140
    ∴ Here, we can see that both the maximum demand and reorder value are equal, service level = 100%

    Correct Option: D

    The expected value of lead time demand
    ⇒ 80 × 0.20 + 100 × 0.25 + 120 × 0.30 + 140 × 0.25 = 112
    Reorder level is 1.25 times the lead time demand.
    So, Reorder value = 1.25 × 112 = 140
    ∴ Here, we can see that both the maximum demand and reorder value are equal, service level = 100%


  1. A residential school stipulates the study hours as 8 : 00 pm to 10 : 30 pm. Warden makes random checks on a certain student 11 occasions a day during the study hours over a period of 10 days and observes that he is studying on 71 occasions. Using 95% confidence interval, the estimated minimum hours of his study during that 10 day period is









  1. View Hint View Answer Discuss in Forum

    Number of total observation in 10 days = 11 × 10 = 110
    No. of observation when studying = 71

    ∴ P =
    71
    = 0.6455
    110

    (Probability of studying)
    Total studying hour in 10 days = (2.5 hr) × 10
    Hence, Minimum no. of hours of studying in 10 days = (25 hr) × p = 25 × 0.6455 = 16.13 hrs.

    Correct Option: C

    Number of total observation in 10 days = 11 × 10 = 110
    No. of observation when studying = 71

    ∴ P =
    71
    = 0.6455
    110

    (Probability of studying)
    Total studying hour in 10 days = (2.5 hr) × 10
    Hence, Minimum no. of hours of studying in 10 days = (25 hr) × p = 25 × 0.6455 = 16.13 hrs.



  1. The expected time (te) of a PERT activity in terms of optimistic time (to), pessimistic time (tp) and most likely time (tl) is given by









  1. View Hint View Answer Discuss in Forum

    NA

    Correct Option: A

    NA


Direction: Consider a PERT network for a project involving six tasks (a to f)

  1. The standard deviation of the critical path of the project is









  1. View Hint View Answer Discuss in Forum

    25 + 81 + 36 + 9 = √151 days.

    Correct Option: A

    25 + 81 + 36 + 9 = √151 days.



  1. The expected completion time of the project is









  1. View Hint View Answer Discuss in Forum


    ⇒ a – c – e – f
    ⇒ 30 + 60 + 45 + 20 = 155 days

    Correct Option: D


    ⇒ a – c – e – f
    ⇒ 30 + 60 + 45 + 20 = 155 days