Industrial Engineering Miscellaneous
- The distribution of lead time demand for an item is as follows :
The reorder level is 1.25 times the expected value of the lead time demand. The service level is
-
View Hint View Answer Discuss in Forum
The expected value of lead time demand
⇒ 80 × 0.20 + 100 × 0.25 + 120 × 0.30 + 140 × 0.25 = 112
Reorder level is 1.25 times the lead time demand.
So, Reorder value = 1.25 × 112 = 140
∴ Here, we can see that both the maximum demand and reorder value are equal, service level = 100%Correct Option: D
The expected value of lead time demand
⇒ 80 × 0.20 + 100 × 0.25 + 120 × 0.30 + 140 × 0.25 = 112
Reorder level is 1.25 times the lead time demand.
So, Reorder value = 1.25 × 112 = 140
∴ Here, we can see that both the maximum demand and reorder value are equal, service level = 100%
- A residential school stipulates the study hours as 8 : 00 pm to 10 : 30 pm. Warden makes random checks on a certain student 11 occasions a day during the study hours over a period of 10 days and observes that he is studying on 71 occasions. Using 95% confidence interval, the estimated minimum hours of his study during that 10 day period is
-
View Hint View Answer Discuss in Forum
Number of total observation in 10 days = 11 × 10 = 110
No. of observation when studying = 71∴ P = 71 = 0.6455 110
(Probability of studying)
Total studying hour in 10 days = (2.5 hr) × 10
Hence, Minimum no. of hours of studying in 10 days = (25 hr) × p = 25 × 0.6455 = 16.13 hrs.Correct Option: C
Number of total observation in 10 days = 11 × 10 = 110
No. of observation when studying = 71∴ P = 71 = 0.6455 110
(Probability of studying)
Total studying hour in 10 days = (2.5 hr) × 10
Hence, Minimum no. of hours of studying in 10 days = (25 hr) × p = 25 × 0.6455 = 16.13 hrs.
- The expected time (te) of a PERT activity in terms of optimistic time (to), pessimistic time (tp) and most likely time (tl) is given by
-
View Hint View Answer Discuss in Forum
NA
Correct Option: A
NA
Direction: Consider a PERT network for a project involving six tasks (a to f)
- The standard deviation of the critical path of the project is
-
View Hint View Answer Discuss in Forum
√25 + 81 + 36 + 9 = √151 days.
Correct Option: A
√25 + 81 + 36 + 9 = √151 days.
- The expected completion time of the project is
-
View Hint View Answer Discuss in Forum
⇒ a – c – e – f
⇒ 30 + 60 + 45 + 20 = 155 daysCorrect Option: D
⇒ a – c – e – f
⇒ 30 + 60 + 45 + 20 = 155 days