Industrial Engineering Miscellaneous
- If at the optimum in a linear programming problem, a dual variable corresponding to a particular primal constraint is zero, then it means that
-
View Hint View Answer Discuss in Forum
NA
Correct Option: C
NA
- In PERT, the distribution of activity times is assumed to be
-
View Hint View Answer Discuss in Forum
NA
Correct Option: C
NA
- A dummy activity is used in PERT network to describe
-
View Hint View Answer Discuss in Forum
Dummy activities often have a zero completion time & are used to represents precendence relationship.
Correct Option: A
Dummy activities often have a zero completion time & are used to represents precendence relationship.
- When the annual demand of a product is 24000 units, the EOQ (Economic Order Quantity) is 2000 units. If the annual demand is 48000 units the most appropriate EOQ will be
-
View Hint View Answer Discuss in Forum
EOQ ∝ √D
EOQ2 = EOQ1 √D2 √D1 EOQ2 = EOQ1 × √D2 √D1 EOQ2 = 2000 × √4800 = 2828 √2400
Correct Option: C
EOQ ∝ √D
EOQ2 = EOQ1 √D2 √D1 EOQ2 = EOQ1 × √D2 √D1 EOQ2 = 2000 × √4800 = 2828 √2400
- A company produces two types of toys: P and Q. Production time of Q is twice that of P and the company has a maximum of 2000 time units per day. The supply of raw material is just sufficient to produce 1500 toys (of any type) per day. Toy type Q requires an electric switch which is available @ 600 pieces per day only. The company makes a profit of Rs. 3 and Rs. 5 on type P and Q respectively. For maximization of profits, the daily production quantities of P and Q toys should respectively be
-
View Hint View Answer Discuss in Forum
Zmax = 3P + 5Q
subject to P + 2Q ≤ 2000
P + Q ≤ 1500
Q ≤ 600
P, Q ≥ 0
Feasible solution (O A B C D)
Since At point A (1500,0)
Z = 3 × 1500 + 5 × 0 = 4500
At Point B (1000, 500)
Z = 3 × 1000 + 5 × 500 = 5500
At point C (800, 600)
Z = 3 × 800 + 5 × 600 = 5400
At Point O (0, 600)
Z = 3 × 0 + 5 × 600 = 3000
Hence Z in maximum at B (1000,500)
P = 1000 units and Q = 500 unitsCorrect Option: A
Zmax = 3P + 5Q
subject to P + 2Q ≤ 2000
P + Q ≤ 1500
Q ≤ 600
P, Q ≥ 0
Feasible solution (O A B C D)
Since At point A (1500,0)
Z = 3 × 1500 + 5 × 0 = 4500
At Point B (1000, 500)
Z = 3 × 1000 + 5 × 500 = 5500
At point C (800, 600)
Z = 3 × 800 + 5 × 600 = 5400
At Point O (0, 600)
Z = 3 × 0 + 5 × 600 = 3000
Hence Z in maximum at B (1000,500)
P = 1000 units and Q = 500 units