Direction: Consider a PERT network for a project involving six tasks (a to f)

  1. The standard deviation of the critical path of the project is
    1. 151 days
    2. 155 days
    3. 200 days
    4. 238 days
Correct Option: A

25 + 81 + 36 + 9 = √151 days.