Direction: Consider a PERT network for a project involving six tasks (a to f)

  1. The standard deviation of the critical path of the project is
    1. √151 days
    2. √155 days
    3. √200 days
    4. √238 days
Correct Option: A

√25 + 81 + 36 + 9 = √151 days.