  1. A firm uses a turning center, a milling center and a grinding machine to produce two parts. The table below provides the machining time required for each part and the maximum machining time available on each machine. The profit per unit on parts I and II are Rs. 40 and Rs. 100, respectively. The maximum profit per week of the firm is Rs. ________
    1. 40,000
    2. 40,00
    3. 30,000
    4. 20,000
Correct Option: A


Zmax =40x + 100y
S.t 12x + 6y ≤ 6000, 4x + 10y ≤ 4000
2x + 3y ≤ 1800 x, y ≥ 0

x
+
y
≤ 1
x
+
y
≤ 1
500 10001000400

x
+
y
≤ 1
900 600

12x + 6y = 6000
4x + 10y = 4000

12x + 6y = 6000
12x + 30y = 12000
- 24y = - 6000

y =
6000
= 250
24

4x + 10y = 4000
4x + 250 × 10 = 4000
4x = 1500
x =
1500
= 375
4

Zmax =40x + 100y
= 40 × 375 + 100 × 250
= 15000 + 25000
ZD = 40,000/-
ZA = 0
ZB = 40 × 500 + 100 × 0
= 20,000
ZC = 40 × 0 + 100 × 400
= 40,000
Optional at (D) & (C).