For butt welding 40 mm thick steel plates, when the expected quantity of such jobs is 5000 per month over a period of 10 years, choose the best suitable welding process out of the following available alternatives.
-
- SAW
- Oxyacetylene gas welding
- EBM
- MIG
- SAW
Correct Option: A
No. of jobs is very high, therefore we need a welding process which is capable of welding in one pass. Therefore, SAW is chosen over others.