Academic Resource
Aptitude
Data Interpretation
Verbal Reasoning
Non Verbal Reasoning
Verbal Ability
Programming
General Knowledge
Puzzle
Engineering
Computer Engineering
Electronics and Communication
Electrical Engineering
Mechanical Engineering
Civil Engineering
Biotechnology
Architecture & Planning
Online Test
Aptitude Test
Data Interpretation Test
Verbal Reasoning Test
Non Verbal Reasoning Test
Verbal Ability Test
Exams
More
Full Forms
Home
»
Architecture and Planning Miscellaneous
»
Architecture and Planning Miscellaneous-topic
» Question
Architecture and Planning Miscellaneous-topic
Easy Questions
Moderate Questions
Difficult Questions
Architecture and Planning Miscellaneous
Architecture and Planning Miscellaneous-topic
From the following cost components of a building construction project which is not a direct cost combination ?
P. Labour cost
Q. Equipment cost
R. Material cost
S. Establishment cost
T. Supervision cost
P and Q
Q and R
P and R
S and T
Correct Option:
D
S and T