  1. A levelling is carried out to establish the Reduced Levels (RL) of point R with respect to the Bench Mark (BM) at P. The staff readings taken are given below.

    If RL of P is + 100.000 m, then RL (in m) of R is
    1. 103.355
    2. 103.155
    3. 101.455
    4. 100.355
Correct Option: C

HI = RL + BS
RL = HI – FS
We find HI & RC from given values
Given RL at P is + 100 m.