  1. In an assembly line for assembling toys, five workers are assigned tasks which take times of 10, 8, 6, 9 and 10 minutes respectively. The balance delay for line is
    1. 43.3%
    2. 14.8%
    3. 14.0%
    4. 16.3%
Correct Option: C

Assuming cycle time = 10 + 8 + 6 + 9 + 10 = 43

Balance delay = 1 -
∑ ti
= 1-
43
= 0.14
n × te5 × 10

= 14%