Home » Industrial Engineering » Industrial Engineering Miscellaneous » Question

Industrial Engineering Miscellaneous

Industrial Engineering

  1. Match the following
    List-I
    (Problem areas)
    List-II
    (Techniques)
    A. JIT 1. CRAFT
    B. Computer assisted 2. PERT layout
    C. Scheduling 3. Johnson's rule
    D. Simulation 4. Kanbans
    5. EOQ rule
    6. Monte Carl
    1. A –4, B–5, C–3, D–1.
    2. A –1, B–5, C–3, D–4.
    3. A –4, B–1, C–3, D–6
    4. A –5, B–2, C–3, D–6
Correct Option: C

(a) JIT – (4) Kanbans (b) Computer –(1) CRAFT Assisted Layout (c) Scheduling –(3) John son’s Rule (d) Simulations – (6) Monte carl
⇒ A –4, B–1, C–3, D–6.



Your comments will be displayed only after manual approval.