  1. The ratio of the amount of work done by (x – 1) labours in (x +1) days and that done by (x +1) labours in (x + 2) days is 5 : 6. Then the value of x is
    1. 16
    2. 15
    3. 17
    4. 14
Correct Option: A

According to the question,

(x – 1)(x + 1)
=
5
(x + 1)(x + 2)6

⇒ 
x – 1
=
5
x + 26

⇒  6x – 6 = 5x + 10
⇒  6x – 5x = 10 + 6
⇒  x = 16