  1. A can do a job in 10 days and B can do the same job in 15 days. They start working together, but B leaves after 5 days. How many more days A want to finish the work ?
    1. 2 days
    2. 1
      2
      days
      3
    3. 3 days
    4. 2
      2
      days
      3
Correct Option: B

Work done by A and B in 5 days

⇒ 5
1
+
1
= 5
3 + 2
101530

= 5 ×
5
=
5
306

Remaining work = 1 –
5
=
1
66

∴ Time taken by A
=
1
× 10 =
5
days = 1
2
days
633