Home » Aptitude » Time and Work » Question
  1. A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is
    1. 20 days
    2. 21 days
    3. 22 days
    4. 24 days
Correct Option: D

A is twice as good as B.
∴ Time taken by A = x days
Time taken by B = 2x days
According to the question,

1
+
1
=
1
x2x16

2 + 1
=
1
2x16

3
=
1
2x16

⇒ x = 3 × 8 = 24 days