Home » Aptitude » Time and Work » Question
  1. A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work.
    How many men can be discharged now so that the work may finish in time ?
    1. 48
    2. 56
    3. 40
    4. 50
Correct Option: B

Using Rule 1,

Remaining work = 1 -
2
=
1
33

Remaining days = 124–64= 60
M1D1
=
M2D2
W1W2

120 × 64
=
M2 × 60
2
1
33

⇒ M2 =
120 × 64
= 64
2 × 60

∴ No. of men can be discharged
= 120 – 64 = 56 men