Correct Option: B
According to the question
Work done by A and B together in one day
Work done by B and C together in one day
Work done by C and A together in one day
So,
Adding I, II, III, we get
2 (A + B + C) = | 1 | + | 1 | + | 1 | |
10 | 15 | 20 |
2 (A + B + C) = | 6 + 4 + 3 | = | 13 | |
60 | 60 |
A + B + C = | 13 | .........(iv) |
120 |
Putting the value of eqn. (I) in eqn. (IV)
C = | 13 | - | 1 | = | 13 - 12 | = | 1 | |
120 | 10 | 120 | 120 |
∴ Work done in 1 day by C is
Hence, C will finish the whole work in 120 days
Aliter : Using Rule 19,
C alone can do the work in
= | 2 × 10 × 15 × 20 | |
10 × 15 - 15 × 20 + 20 × 10 |