A can do a piece of work in 40 days. He works on it for 5 days and then B completes it in 21 days. How long will A and B together take to complete the work?
-
- 10 days
- 15 days
- 20 days
- 25 days
Correct Option: B
Using Rule 2,
A’s 1 day’s work = | 40 |
∴ A’s 5 days’ work
= | = | |||
40 | 8 |
Remaining work
= 1 - | = | |||
8 | 8 |
This part of work is done by B in 21 days.
∴ B’s 1 day’s work
= | = | |||
8 × 21 | 24 |
∴ (A + B)’s 1 day’s work
= | + | = | ||||
40 | 24 | 120 |
= | = | |||
120 | 15 |
Hence, A and B together will
complete the work in 15 days.