  1. A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
    1. 3
    2. 5
    3. 10
    4. 12l
Correct Option: A

Work done by A and B in 5 days = 5
1
+
1
= 5
5 + 4
121560

Work done by A and B in 5 days = 5 ×
9
=
9
=
3
60124

Remaining work = 1 -
3
=
1
44

∴ Time taken by A =
1
× 12 = 3 days.
4

Second method to solve this question ,
Here, m = 12, n = 15,p = 5
Time taken by A =
mn - p (m + n)
days
n

Time taken by A =
12 × 15 - 5(12 + 15)
15

Time taken by A =
180 - 135
= 3 days
15