Home » Aptitude » Time and Work » Question
  1. A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharge now, so that the work finish in time ?
    1. 40
    2. 50
    3. 48
    4. 56
Correct Option: D

Given, M1 = 120, M2 = 120 - n, D1 = 64, D2 = 60
W1= 2/3 and W2 = 1/3
According to the formula,
(M1D1) / W1 = (M2D2) / W2
⇒ [120 x (64/2)] / 3 = [(120 - n) x 60] / (1/3)
⇒ (120 x 64) / (2 x 60) = (120 - n)
⇒ (120 - n) = 64
∴ n = 120 - 64 = 56
Now, 56 men can be discharged to finish the work in time.