Some persons can do a piece of work in 12 days. Two times the number of such persons will do half of that work in :
-
- 16
- 12
- 8
- 3
Correct Option: D
Let M men can do the in 12 days and the required number of days be D.
More men, Less days [ Indirect Proportion ]
Less work, Less days [ Direct Proportion ]
By chain rule ,
⇒ 2M x 1 x D = M x | 1 | x 12 |
2 |
⇒ D = 3 days
Thus , required answer is 3 days .