  1. Some persons can do a piece of work in 12 days. Two times the number of such persons will do half of that work in :
    1. 16
    2. 12
    3. 8
    4. 3
Correct Option: D

Let M men can do the in 12 days and the required number of days be D.
More men, Less days [ Indirect Proportion ]
Less work, Less days [ Direct Proportion ]
By chain rule ,

⇒ 2M x 1 x D = M x 1 x 12
2

⇒ D = 3 days
Thus , required answer is 3 days .