  1. A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After 30 days, 25 % of the work is completed. How many additional persons should be deployed so that the work will be completed in the scheduled time, each person now working 9 hours a day.
    1. 60
    2. 58
    3. 12
    4. 56
Correct Option: D