A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After 30 days, 25 % of the work is completed. How many additional persons should be deployed so that the work will be completed in the scheduled time, each person now working 9 hours a day.
-
- 60
- 58
- 12
- 56
Correct Option: D
According to question ,