Home » Aptitude » Work and Wages » Question
  1. A can do a piece of work in 8 days. A undertook to it for $320. With the help of B, he finishes the work in 6 days. B’s share is:
    1. $80
    2. $240
    3. $100
    4. $120
Correct Option: A

As we know that ,
Here, Total amount = $320

(A + B)’s 1 day’s work =1
6
A’s 1 days’ work =1
8

∴ B’s 1 days’ work = (A + B)’s 1 day’s work - A’s 1 days’ work
B’s 1 days’ work =
1
-
1
=
1
6 8 24

∴ Money should be divided in the ratio =
1
:
1
= 3 : 1
8 24
∴ B gets = $
B 's ratio
x Total amount
Sum of both ratios
∴ B gets = $
1
x 320= $ 80
4