  1. A and B together can do a work in 8 days. If A alone can do it in 12 days, then in how many days can B alone do it ?
    1. 12 days
    2. 20 days
    3. 24 days
    4. 28 days
Correct Option: C

Required time taken by B to complete the work = xy / x - y
[Here x = 12 and y = 8]
⇒ required time = (12 x 8) / (12 - 8) = 96/4 = 24 days